The Work of Project Execution

So far, the discussion has been pretty general concerning the work of project execution. Until now, it has simply been characterized as "successfully execute some tasks." Let's get specific now and talk about the types of work that get done while you execute your project.

Types of Work

The types of work include the following:

  • Performing the tasks of the project—First and foremost, you and your team must perform every task of the WBS in the sequence that you laid out in your network diagram. You must do all this work with the intention of fulfilling the objectives that were originally requested of your project. You must course-correct if you perform the tasks that have been planned and they are not fulfilling the objectives of the project.
  • Staffing the project—You must staff the project as the need arises. You have already determined who will do what task. Now is the time to bring these people to the project and put them to work. You might need to provide some type of orientation to get these people ready to work and perform effectively.
  • Training resources—You might also have to supplement your project resources' skills. Some team members might need a specific piece of training to work effectively. Every resource might need some level of training if you are working in a brand-new technology or process discipline.
  • Managing human resources—You are accountable for the performance of the resources on your project, regardless of the type of organization that you work in (projectized, matrixed, or functional). Thus, you must manage the resources. You must assign tasks, overcome roadblocks, follow up on work, and provide feedback. You must gather documentation on the performance of each team member and provide that to other supervisors at the end of the project.
  • Managing other resources—You also must manage your resources during execution if you plan to use other types of resources. You must make sure that the bulldozer you need for Task 57 is delivered just before that task. You also must make sure that it is returned as soon as Task 57 is completed so you don't pay late fees and expend more of your budget than was allocated.
  • Installing methods and procedures—You might have done some very detailed planning on certain tasks while you were planning the project. This detail might include things such as step-by-step methods or procedures for getting the work done the right way. Now is the time to implement any of these work methods.
  • Collecting work performance information—Earlier in this chapter, you established a status meeting as you set the rhythm of the project. Here is where you collect information from each team member regarding how the work is being performed. I talk about exactly what information you will collect in the next chapter, on monitoring and controlling the project.
  • Reporting on project information—You must accumulate data regarding the performance of the project tasks. You must report on the data you've gathered, depending on your organization's requirements for status reports. Even if your organization has no reporting requirements, you must provide reports based on what you have defined in your communication plan.
  • Executing your communication plan—You also start to execute your communication plan. You must determine which elements of your plan need to be done at what point in time while the project is being executed.
  • Implementing approved changes—You'll find that as you and your team execute the project plan, someone might ask for changes to what has been originally planned. These requests for changes will go through an entire process that we describe in Chapter 13. Some will be denied, and some will be approved. Those that are approved will be completed as part of your execution process.
  • Validating project deliverables—As the team creates the product of the project, you must control the creation of those deliverables. You also must spend some time validating those deliverables back to the original request or requirements.
  • Gathering lessons learned—A lot of organizations collect lessons learned at the end of the project. Organizations that are adopting industry best practices are finding that it's best to collect lessons learned all the way through the project. That way, the team members learn from their mistakes right away and have a chance to correct some of their problems along the way instead of waiting until the next project. This also allows the team to find out what they are doing right so they have a chance to continue with that winning performance.
  • Performing risk management—The team has a chance to manage the risks identified in the planning stage as the project tasks are being performed. The team members can put their response plans into place. This is also the time to gather new risks and continue managing the top 25 percent on the master risk identification list.

And all you thought you were going to do was manage the completion of the project tasks! You probably feel like a juggler right now trying to figure out exactly how you will accomplish all of this. Is that you in Figure 11.4? Not to worry, though. You have everything covered in your project plan if you have done the level of planning that I have discussed all the way through this book. In it, you have documented every aspect of the planning, from how you will perform risk management to what training is needed for every resource on the project. Oh, you say I haven't covered that yet? Well, this is covered in the "Teaming" section of this chapter.

Figure 11.4

Figure 11.4 Juggling the work of execution

You need to do one more piece of work while you are executing your project: a quality audit.

Quality Audits

You laid out activities that your resources must perform to guarantee the quality of the product you are creating. You execute those quality activities during the execution of your project. You might also find that the activities you have planned for quality are not substantial enough to guarantee the quality. How will you know if you need to implement more quality activities? A quality audit is the answer.

A quality audit is a review that determines whether the project is complying with the quality standards that were set in the planning stage of the project. Someone outside the project team usually does the quality audit, to be objective in a review of the project.

The auditor looks at two different sets of information in this review:

  • The product of the project—The auditor will verify that the product of the project is meeting the requirements that have been created to describe the product. The auditor will also verify that the procedures for creating the product are being used successfully.
  • The processes of the project—The auditor will review the processes of the project and determine whether they are being performed correctly. The auditor will also conduct an analysis to make sure that these processes are sufficient to manage the project to a successful completion.

The objective of the quality audit is to look for ineffective and inefficient processes and procedures that will hamper the quality of the product and the project. Remember, the objective of the project is to deliver to the triple constraints of the MOP, cost, and time. You won't fulfill the triple constraints if your project processes are not working.

Now let's talk about the timing of quality audits. You need to perform a quality audit at least twice on your project. You might even need more than two audits, depending on the length of the project.

The first audit is performed at the end of the planning stage and the beginning of the execution stage of your project. This audit inspects the processes and procedures that have been designed for the execution stage. The auditor does a document check to verify what was created and make sure that the documents are sufficient for the size and complexity of your project. The team should immediately institute any recommendations that the auditor provides, before the team gets into the habit of executing an inefficient process.

The second quality audit should be performed after the team has been working on project execution for a while. Here the auditor makes sure that the processes is being executed correctly. The auditor also inspects the deliverables of the process to make sure the process is producing the right quality of deliverable.

You can see now why more than two audits might be needed. A project with a year length might be starting a new deliverable every couple of months. You might consider bringing in an auditor shortly after work begins on the next major deliverable, if your project can afford it.

Another way to use a quality audit is in response to problems. Perform an audit when you start to see variance in the work being done. Bringing in an auditor when you start to see problems can be a diagnostic tool before your project really goes way off track. I talk more about this in the next chapter.

Another important activity of project execution is developing the project team. Let's move on to the "Teaming" section and talk about team development.

InformIT Promotional Mailings & Special Offers

I would like to receive exclusive offers and hear about products from InformIT and its family of brands. I can unsubscribe at any time.

Overview


Pearson Education, Inc., 221 River Street, Hoboken, New Jersey 07030, (Pearson) presents this site to provide information about products and services that can be purchased through this site.

This privacy notice provides an overview of our commitment to privacy and describes how we collect, protect, use and share personal information collected through this site. Please note that other Pearson websites and online products and services have their own separate privacy policies.

Collection and Use of Information


To conduct business and deliver products and services, Pearson collects and uses personal information in several ways in connection with this site, including:

Questions and Inquiries

For inquiries and questions, we collect the inquiry or question, together with name, contact details (email address, phone number and mailing address) and any other additional information voluntarily submitted to us through a Contact Us form or an email. We use this information to address the inquiry and respond to the question.

Online Store

For orders and purchases placed through our online store on this site, we collect order details, name, institution name and address (if applicable), email address, phone number, shipping and billing addresses, credit/debit card information, shipping options and any instructions. We use this information to complete transactions, fulfill orders, communicate with individuals placing orders or visiting the online store, and for related purposes.

Surveys

Pearson may offer opportunities to provide feedback or participate in surveys, including surveys evaluating Pearson products, services or sites. Participation is voluntary. Pearson collects information requested in the survey questions and uses the information to evaluate, support, maintain and improve products, services or sites, develop new products and services, conduct educational research and for other purposes specified in the survey.

Contests and Drawings

Occasionally, we may sponsor a contest or drawing. Participation is optional. Pearson collects name, contact information and other information specified on the entry form for the contest or drawing to conduct the contest or drawing. Pearson may collect additional personal information from the winners of a contest or drawing in order to award the prize and for tax reporting purposes, as required by law.

Newsletters

If you have elected to receive email newsletters or promotional mailings and special offers but want to unsubscribe, simply email information@informit.com.

Service Announcements

On rare occasions it is necessary to send out a strictly service related announcement. For instance, if our service is temporarily suspended for maintenance we might send users an email. Generally, users may not opt-out of these communications, though they can deactivate their account information. However, these communications are not promotional in nature.

Customer Service

We communicate with users on a regular basis to provide requested services and in regard to issues relating to their account we reply via email or phone in accordance with the users' wishes when a user submits their information through our Contact Us form.

Other Collection and Use of Information


Application and System Logs

Pearson automatically collects log data to help ensure the delivery, availability and security of this site. Log data may include technical information about how a user or visitor connected to this site, such as browser type, type of computer/device, operating system, internet service provider and IP address. We use this information for support purposes and to monitor the health of the site, identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents and appropriately scale computing resources.

Web Analytics

Pearson may use third party web trend analytical services, including Google Analytics, to collect visitor information, such as IP addresses, browser types, referring pages, pages visited and time spent on a particular site. While these analytical services collect and report information on an anonymous basis, they may use cookies to gather web trend information. The information gathered may enable Pearson (but not the third party web trend services) to link information with application and system log data. Pearson uses this information for system administration and to identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents, appropriately scale computing resources and otherwise support and deliver this site and its services.

Cookies and Related Technologies

This site uses cookies and similar technologies to personalize content, measure traffic patterns, control security, track use and access of information on this site, and provide interest-based messages and advertising. Users can manage and block the use of cookies through their browser. Disabling or blocking certain cookies may limit the functionality of this site.

Do Not Track

This site currently does not respond to Do Not Track signals.

Security


Pearson uses appropriate physical, administrative and technical security measures to protect personal information from unauthorized access, use and disclosure.

Children


This site is not directed to children under the age of 13.

Marketing


Pearson may send or direct marketing communications to users, provided that

  • Pearson will not use personal information collected or processed as a K-12 school service provider for the purpose of directed or targeted advertising.
  • Such marketing is consistent with applicable law and Pearson's legal obligations.
  • Pearson will not knowingly direct or send marketing communications to an individual who has expressed a preference not to receive marketing.
  • Where required by applicable law, express or implied consent to marketing exists and has not been withdrawn.

Pearson may provide personal information to a third party service provider on a restricted basis to provide marketing solely on behalf of Pearson or an affiliate or customer for whom Pearson is a service provider. Marketing preferences may be changed at any time.

Correcting/Updating Personal Information


If a user's personally identifiable information changes (such as your postal address or email address), we provide a way to correct or update that user's personal data provided to us. This can be done on the Account page. If a user no longer desires our service and desires to delete his or her account, please contact us at customer-service@informit.com and we will process the deletion of a user's account.

Choice/Opt-out


Users can always make an informed choice as to whether they should proceed with certain services offered by InformIT. If you choose to remove yourself from our mailing list(s) simply visit the following page and uncheck any communication you no longer want to receive: www.informit.com/u.aspx.

Sale of Personal Information


Pearson does not rent or sell personal information in exchange for any payment of money.

While Pearson does not sell personal information, as defined in Nevada law, Nevada residents may email a request for no sale of their personal information to NevadaDesignatedRequest@pearson.com.

Supplemental Privacy Statement for California Residents


California residents should read our Supplemental privacy statement for California residents in conjunction with this Privacy Notice. The Supplemental privacy statement for California residents explains Pearson's commitment to comply with California law and applies to personal information of California residents collected in connection with this site and the Services.

Sharing and Disclosure


Pearson may disclose personal information, as follows:

  • As required by law.
  • With the consent of the individual (or their parent, if the individual is a minor)
  • In response to a subpoena, court order or legal process, to the extent permitted or required by law
  • To protect the security and safety of individuals, data, assets and systems, consistent with applicable law
  • In connection the sale, joint venture or other transfer of some or all of its company or assets, subject to the provisions of this Privacy Notice
  • To investigate or address actual or suspected fraud or other illegal activities
  • To exercise its legal rights, including enforcement of the Terms of Use for this site or another contract
  • To affiliated Pearson companies and other companies and organizations who perform work for Pearson and are obligated to protect the privacy of personal information consistent with this Privacy Notice
  • To a school, organization, company or government agency, where Pearson collects or processes the personal information in a school setting or on behalf of such organization, company or government agency.

Links


This web site contains links to other sites. Please be aware that we are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of each and every web site that collects Personal Information. This privacy statement applies solely to information collected by this web site.

Requests and Contact


Please contact us about this Privacy Notice or if you have any requests or questions relating to the privacy of your personal information.

Changes to this Privacy Notice


We may revise this Privacy Notice through an updated posting. We will identify the effective date of the revision in the posting. Often, updates are made to provide greater clarity or to comply with changes in regulatory requirements. If the updates involve material changes to the collection, protection, use or disclosure of Personal Information, Pearson will provide notice of the change through a conspicuous notice on this site or other appropriate way. Continued use of the site after the effective date of a posted revision evidences acceptance. Please contact us if you have questions or concerns about the Privacy Notice or any objection to any revisions.

Last Update: November 17, 2020