Home > Articles > Home & Office Computing > Microsoft Applications

This chapter is from the book

Selecting the Environment Options

Microsoft Project makes many assumptions regarding projects. You can review these default settings, which control the behavior of the application, in the Options dialog box. The options are divided into two types: global and file-specific options. To display the Options dialog box (see Figure 3.8), choose Tools, Options. The options in this dialog box are conveniently organized into categories on a number of tabs.

Figure 3.8 The View tab is the default tab in the Options dialog box.

Most of the settings in the Options dialog box affect the way you view all projects and are referred to as global options. Changes you make to global options affect projects that have already been created, the current project you are working on, and any future projects you create. For example, changing the date format (which might include hours and minutes instead of just rounding to the day) affects all projects, including those that you originally created with a different date format. The new format remains in effect for all projects until you change the setting again.

Some of the options in the Options dialog box are specific to the file you are currently working with. These options include the filename in the section title. For example, the dialog box in Figure 3.8 shows three sections that contain file-specific options: Cross Project Linking Options for 'New Product,' Currency Options for 'New Product,' and Outline Options for 'New Product.' Changes made to these settings affect only the current project you are working on—in this case New Product.mpp. Any options that are not part of a section or for which the section title does not include the filename in the title (such as the Show section in Figure 3.8) are global options.

The Cross Project Linking Options For section of the View tab controls links between projects. For example, the setting in this section in Figure 3.8 are set for the active file only—the default is to display all external links. In addition, when you attempt to open a file that contains links to other projects, a dialog box alerts you that the file has external links.

Selecting the Show Outline Number option in the View tab of the Options dialog box displays the task list of the project in a traditional Work Breakdown Structure (WBS) outline format, tying the schedule of the project to a previously defined scope of work. This is useful to ensure that all the necessary work of the project has been captured.

Also, when you select the option to display a project summary task, a roll-up summary task (numbered 0) appears at the top of the Gantt Chart view and spans the entire duration of the project you have created. Many times, Project users create this manually by indenting, or demoting, all subsequent tasks to the first one, simply because they are not aware of this feature.

NOTE

If the Office Assistant is active, the external link message appears in an Office Assistant pop-up.

In some cases, file-specific options can be changed for the current file and new files if the section containing the file-specific settings has a Set as Default button (see Figure 3.9). If you click the Set as Default button, Project updates the Global template to reflect the option settings. The Global template controls the settings for all new project files. The current document, as well as all new project documents, incorporates these options, but previously created documents do not change.

Figure 3.9 The Edit tab of the Options dialog box has two sections that include Set as Default buttons.

The following sections focus on a few choices in the Options dialog box that are critical in defining any new project and a few options of general interest.

NOTE

All changes you make in the Options dialog box are saved in the Windows Registry.

Reviewing Critical Options

There are several important settings on the Calendar tab that you should confirm are appropriate for your organization. These options determine how the calendar is used on printed reports, how your fiscal year is designated, and, most importantly, how your use of the terms day, week, and month are interpreted by Microsoft Project. Figure 3.10 shows the settings on the Calendar tab.

Figure 3.10 The Calendar tab of the Options dialog box enables you to customize project plan settings to your organization's working hours.

Defining Days, Weeks, and Months

The three most critical settings are those that define the meaning of the basic task duration units—days, weeks, and months. The fundamental unit of time in Microsoft Project is the minute. When you enter any other unit for a task duration, Project internally converts these terms into minutes, based on the definitions in the Options dialog box. All calculations dealing with duration are carried out in minutes. When you ask Microsoft Project to display a task duration in days, weeks, or months, Project uses these settings to convert the display. Therefore, the options Hours per Day, Hours per Week, and Days per Month are crucial to the interpretation and display of your estimates of task duration (refer to Figure 3.10).

Thus, for example, if you estimate a task duration to be 2 days, Project uses the entry in the Hours per Day text box to internally set the duration to minutes. If the Hours per Day entry is 8.00, the duration is recorded as 960 minutes (that is, 2 daysx8 hours/dayx60 minutes/hour). If the Hours per Day entry is 10.00 and you estimate the duration to be 2 days, then the task duration is recorded as 1,200 minutes, which is much more work than if the Hours per Day entry is 8.00.

You need to make sure these settings are appropriate for your organization. For example, if you work for an organization that has a 4-day work week (that is, each employee works 10-hours per day for 4 days each week), you should change the Hours per Day field to 10 and leave the Hours per Week field at 40. If your organization is open 8 hours per day Monday through Friday and 1?2 day Saturday, you might prefer to change the Hours per Week to 44 so that when you estimate a task to take a week, the duration means the same thing to Microsoft Project as it does to you.

Note that the definition of the task duration is set at the time you estimate it, according to the definition of the terms you use (day, week, or month). If you later change the definition of a day, for example, to be 10 instead of 8 hours, Project does not change the minutes defined for each task duration. However, the display of those minutes in days or weeks is affected.

The Project Management Institute (PMI) suggests that no task be longer than 80 hours (or 2 weeks' duration, based on a 40-hours-per-week calendar). In other words, the work should be broken down to increments that are no longer than this span of time.

Also, defining months can be difficult because it is typically an inconsistent measure of time, so it's better to use hour or week duration units.

CAUTION

If you change the definitions for a day, week, or month after you enter the project data, Microsoft Project doesn't redefine the minute duration of tasks; it merely displays these minutes as a different number of days or weeks. For example, if you originally entered the duration of a task to be 1 week (at 40 hours per week) and later changed the number of hours in a week on the Calendar tab from 40 to 44 hours, the duration for the task would read .91w. The task would still be 40 hours, but 1 week would now be equal to 44 hours, not 40. This is one reason for establishing option settings before entering task and duration information.

→ To learn how Microsoft Project interprets duration, see "Creating a Task List," p. 119.

Defining the Default Start and End Time of Day

When you define the working days, hours, and months for the Standard calendar (see "Defining a Calendar of Working Time," later in this chapter), you define the hour when work normally begins and ends. It's important that you also record those standards in the Default Start Time and Default End Time text boxes on the Calendar tab of the Options dialog box. Microsoft Project uses these settings in several places:

  • When you specify the date but not the time for the start or finish date of the project in the Project Information dialog box.

  • When you put a constraint on a task, such as Finish No Later Than.

  • When you begin tracking the actual work on the project.

For example, say that the normal work hours for an organization are 7:00 a.m. to 4:00 p.m. If you define these hours in your Standard calendar but leave the setting for Default Start Time at 8:00 a.m., Microsoft Project schedules the first task in the project to start 1 hour later than the actual start of work.

In addition, when you use the Tracking toolbar buttons to designate the percentage completed for a task, the time a task started is assumed to be the default start time from the Calendar tab in the Options dialog box. Even though time might not be displayed as part of the Start Date field format, it is stored with the date. So if the standard calendar hours are from 7:00 a.m. to 4:00 p.m. and you mark a task as 100% complete, the actual start date shows the task starting at 8:00 a.m. and the actual finish date shows the task ending the next day at 8:00 a.m. If only the dates and not the time are displayed in the Start and Finish Date fields in the Gantt Chart view, it appears that there is an error—a task with a duration of 1 day (8 hours) starts on one day but ends on the next day. The culprit is typically an inconsistency between the time used on the Standard calendar and the time designated on the Calendar tab of the Options dialog box.

TIP

It is a good idea to display a date format that also displays time. The Date Format setting is on the View tab of the Options dialog box.

If you change the default start and end times, be careful to coordinate these time settings with the Standard calendar you create for your organization.

Defining the Start of the Fiscal Year

The name of the month that begins the fiscal year is a critical option. This choice affects displays and reports that show annual and quarterly amounts. If the fiscal year begins in October, for example, you might want all reports to include October through December figures in first-quarter totals and the annual figures to be calculated by using the October through September figures. The Fiscal Year setting is on the Calendar tab of the Options dialog box.

By default, the fiscal year is assumed to be numbered by the year in which the fiscal year ends. Therefore, the year in which the fiscal year ends will be used with all months in that fiscal year. For instance, if the fiscal year begins October 2003 and ends September 2004, then the actual calendar month November 2003 would belong in the fiscal year that ends in 2004.

On the Calendar tab, you have the option to have the fiscal year numbering use the starting year instead of the ending year (see Figure 3.11). If you select the Use Starting Year for FY Numbering check box, a fiscal year running from October 2003 to September 2004 would have the calendar month of February 2004 belong in fiscal year 2003; the second quarter of fiscal year 2003 would be the calendar months January, February, and March 2004.

Figure 3.11 You can change the Fiscal Year Starts In option if you want to set some month other than January as the beginning of the fiscal year.

TIP

The Fiscal Year Starts In and Use Starting Year for FY Numbering settings are file-specific settings. If you want to change these settings for all future project files as well as the active file, click the Set as Default button near the bottom of the dialog box.

In some previous versions of Microsoft Project, changing the Fiscal Year Starts In setting in the Options dialog changed the display of the calendar in the timescale of the Gantt Chart view; since Project 2000, this has not been the case. You can either retain the calendar year or show the fiscal year. To choose whether to retain the calendar year or show the fiscal year, you must access the Timescale dialog box by either choosing Format, Timescale or right-clicking the timescale headings in the Gantt Chart view and choosing Timescale from the shortcut menu. The Timescale dialog box appears. To display the fiscal year instead of the calendar year, click the Use Fiscal Year check box (see Figure 3.12).

Figure 3.12 The timescale headings can display fiscal years instead of calendar years.

You can display the fiscal year on either the major or minor scale of the timescale, which is the first or second calendar displayed. A useful display would be to have the fiscal year on one scale and the calendar year on the other scale, using the same unit for both scales.

NOTE

You can only change settings in the timescale of the current view. To update the timescale in another view, such as the Task Usage or Resource Usage view, you have to display that view and change the Timescale settings there.

The timescale display in the Gantt Chart view uses fiscal year numbers instead of calendar year numbers only when the timescale is formatted to display the year, not when displaying months or days.

Setting Options in the Calendar Tab

To set critical calendar preferences, follow these steps:

  1. Choose Tools, Options. The Options dialog box appears.

  2. Click the Calendar tab.

  3. If your fiscal year does not start in January, select the correct month from the Fiscal Year Starts In drop-down list. The default is for the next calendar year to be the fiscal year.

  4. If your work day doesn't start at 8:00 a.m., enter the appropriate time in the Default Start Time text box. You can enter time in 12-hour or 24-hour format. If you use the 12-hour format, be sure to add p.m. to hours past noon (and remember that noon itself is 12:00 p.m.).

  5. Change the Hours per Day, Hours per Week, or Days per Month fields, if necessary, to accurately represent your organization.

TIP

Some organizations change the hours to reflect the hours they expect to work on the project minus the hours needed for other activities (for example, to account for meetings that normally happen in the course of a 40-hour work week). You might change Hours per Day to 6h, allowing 2 hours per day for other activities. This type of change is a judgment call on your part. If you change the hours in this way, make sure the Hours per Week and Hours per Month fields are changed as well.

Companies typically split the day as 75% (for example, 6 hours/day, 30 hours/wk) productive time, or time worked on project-related tasks, and 25% (for example, 2 hours/day, 10 hours/wk) administrative time, or time for office-related tasks. Some companies expect a 45-hour work week in which 8 hours per day are billable and 1 hour is set aside for administrative matters.

When you're planning your project, it's best to consider the specifics of how your organization operates—or how your particular project will work.

  1. Click the Set as Default button to make the values you entered for Fiscal Year Starts In, Default Start Time, Default End Time, Hours per Day, Hours per Week, and Days per Month the default values for all new project documents.

  2. When you are finished, click the OK button.

Setting Other Useful Options

You can change other settings to make data entry easier. It is a good idea to review the current settings in the Options dialog box for each of the following items:

  • Click the General tab to confirm that your name is in the User Name text box. Project uses this name for the Author and Last Saved By properties of the document.

  • Click the Schedule tab to select the time unit you plan to use most often when estimating task duration (see Figure 3.13). Choose the Duration Is Entered In drop-down list to select Minutes, Hours, Days, Weeks, or Months. The Duration setting provides Microsoft Project with instructions about the unit of time to use if you enter a task duration without specifying the unit of time. For example, suppose most of your tasks will have the duration listed in days, and you have selected Days as the time unit in the Duration Is Entered In list box. In the Gantt Chart view, if you enter a 2 in the Duration column, Project records the task duration as 2d (that is, 2 days). Any other duration type has to be entered manually. For example, you would enter a task with a duration of 3 weeks as 3w.

  • Click the View tab to change the default view for new projects. If you prefer to work in a view such as the Network Diagram view or the Task Sheet view—rather than the Gantt Chart view—when starting a new project, change the Default View setting (see Figure 3.14).

Figure 3.13 You can set the de-fault time unit you want used for displaying task duration.

Figure 3.14 You can set the default view on the View tab.

  • On the View tab, choose Date Format to specify how to display dates. The default format displays the date, with the day of the week. The Date Format list box provides alternative format options (such as the date and time together or just the date).

TIP

You can use the Control Panel to set the international regional style for entering date and time. To change the regional date and time formats, open the Windows Start menu and choose Settings, Control Panel. In the Control Panel folder, choose Regional Settings to display the Regional Settings dialog box. Choose the Date and Time tabs, and then make your selections.

  • On the View tab, choose the Decimal Digits text box in the Currency Options Format section to specify the number of decimal points to use in displaying money amounts. The preset value is two decimal points, but you can change that to zero to suppress decimal-point display. As mentioned previously, you can use the Regional Settings dialog box in the Control Panel to select currency units and decimal display.

  • In Microsoft Project views that contain tables (such as the Gantt Chart view), the Enter key causes the selection to advance automatically to the cell below—for example, when you type data in a sheet column, such as the left side of the Gantt Chart view or the Resource Sheet view. You can turn off this feature by deselecting the Move Selection After Enter check box on the Edit tab.

TIP

Many users enter tasks by typing the activity name, tabbing to the right to enter the duration, and then returning to the left to enter the next task name. Because Project won't automatically return to the next line and requires you to select the next task name field with the mouse or arrow keys, you might find it helpful to select the range of cells that you are entering tasks into. When you do so, the Tab key advances the selection to the right and then back to the left after the duration has been typed.

  • Click the Save tab to change the default save format and path (see Figure 3.15). For example, if you want to save all your Project files as Microsoft Project templates or in a previous version of Microsoft Project, click the Save Microsoft Project Files As drop-down and choose one of the listed options. You can also designate the default path where your Project files should be stored. The original default is C:\My Documents. From the File Locations list box, select the file type you want to change, and then click Modify to identify another path.

Figure 3.15 You use the Save tab to set save options, including the default save location, where to store templates, and autosave and database save features.

InformIT Promotional Mailings & Special Offers

I would like to receive exclusive offers and hear about products from InformIT and its family of brands. I can unsubscribe at any time.

Overview


Pearson Education, Inc., 221 River Street, Hoboken, New Jersey 07030, (Pearson) presents this site to provide information about products and services that can be purchased through this site.

This privacy notice provides an overview of our commitment to privacy and describes how we collect, protect, use and share personal information collected through this site. Please note that other Pearson websites and online products and services have their own separate privacy policies.

Collection and Use of Information


To conduct business and deliver products and services, Pearson collects and uses personal information in several ways in connection with this site, including:

Questions and Inquiries

For inquiries and questions, we collect the inquiry or question, together with name, contact details (email address, phone number and mailing address) and any other additional information voluntarily submitted to us through a Contact Us form or an email. We use this information to address the inquiry and respond to the question.

Online Store

For orders and purchases placed through our online store on this site, we collect order details, name, institution name and address (if applicable), email address, phone number, shipping and billing addresses, credit/debit card information, shipping options and any instructions. We use this information to complete transactions, fulfill orders, communicate with individuals placing orders or visiting the online store, and for related purposes.

Surveys

Pearson may offer opportunities to provide feedback or participate in surveys, including surveys evaluating Pearson products, services or sites. Participation is voluntary. Pearson collects information requested in the survey questions and uses the information to evaluate, support, maintain and improve products, services or sites, develop new products and services, conduct educational research and for other purposes specified in the survey.

Contests and Drawings

Occasionally, we may sponsor a contest or drawing. Participation is optional. Pearson collects name, contact information and other information specified on the entry form for the contest or drawing to conduct the contest or drawing. Pearson may collect additional personal information from the winners of a contest or drawing in order to award the prize and for tax reporting purposes, as required by law.

Newsletters

If you have elected to receive email newsletters or promotional mailings and special offers but want to unsubscribe, simply email information@informit.com.

Service Announcements

On rare occasions it is necessary to send out a strictly service related announcement. For instance, if our service is temporarily suspended for maintenance we might send users an email. Generally, users may not opt-out of these communications, though they can deactivate their account information. However, these communications are not promotional in nature.

Customer Service

We communicate with users on a regular basis to provide requested services and in regard to issues relating to their account we reply via email or phone in accordance with the users' wishes when a user submits their information through our Contact Us form.

Other Collection and Use of Information


Application and System Logs

Pearson automatically collects log data to help ensure the delivery, availability and security of this site. Log data may include technical information about how a user or visitor connected to this site, such as browser type, type of computer/device, operating system, internet service provider and IP address. We use this information for support purposes and to monitor the health of the site, identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents and appropriately scale computing resources.

Web Analytics

Pearson may use third party web trend analytical services, including Google Analytics, to collect visitor information, such as IP addresses, browser types, referring pages, pages visited and time spent on a particular site. While these analytical services collect and report information on an anonymous basis, they may use cookies to gather web trend information. The information gathered may enable Pearson (but not the third party web trend services) to link information with application and system log data. Pearson uses this information for system administration and to identify problems, improve service, detect unauthorized access and fraudulent activity, prevent and respond to security incidents, appropriately scale computing resources and otherwise support and deliver this site and its services.

Cookies and Related Technologies

This site uses cookies and similar technologies to personalize content, measure traffic patterns, control security, track use and access of information on this site, and provide interest-based messages and advertising. Users can manage and block the use of cookies through their browser. Disabling or blocking certain cookies may limit the functionality of this site.

Do Not Track

This site currently does not respond to Do Not Track signals.

Security


Pearson uses appropriate physical, administrative and technical security measures to protect personal information from unauthorized access, use and disclosure.

Children


This site is not directed to children under the age of 13.

Marketing


Pearson may send or direct marketing communications to users, provided that

  • Pearson will not use personal information collected or processed as a K-12 school service provider for the purpose of directed or targeted advertising.
  • Such marketing is consistent with applicable law and Pearson's legal obligations.
  • Pearson will not knowingly direct or send marketing communications to an individual who has expressed a preference not to receive marketing.
  • Where required by applicable law, express or implied consent to marketing exists and has not been withdrawn.

Pearson may provide personal information to a third party service provider on a restricted basis to provide marketing solely on behalf of Pearson or an affiliate or customer for whom Pearson is a service provider. Marketing preferences may be changed at any time.

Correcting/Updating Personal Information


If a user's personally identifiable information changes (such as your postal address or email address), we provide a way to correct or update that user's personal data provided to us. This can be done on the Account page. If a user no longer desires our service and desires to delete his or her account, please contact us at customer-service@informit.com and we will process the deletion of a user's account.

Choice/Opt-out


Users can always make an informed choice as to whether they should proceed with certain services offered by InformIT. If you choose to remove yourself from our mailing list(s) simply visit the following page and uncheck any communication you no longer want to receive: www.informit.com/u.aspx.

Sale of Personal Information


Pearson does not rent or sell personal information in exchange for any payment of money.

While Pearson does not sell personal information, as defined in Nevada law, Nevada residents may email a request for no sale of their personal information to NevadaDesignatedRequest@pearson.com.

Supplemental Privacy Statement for California Residents


California residents should read our Supplemental privacy statement for California residents in conjunction with this Privacy Notice. The Supplemental privacy statement for California residents explains Pearson's commitment to comply with California law and applies to personal information of California residents collected in connection with this site and the Services.

Sharing and Disclosure


Pearson may disclose personal information, as follows:

  • As required by law.
  • With the consent of the individual (or their parent, if the individual is a minor)
  • In response to a subpoena, court order or legal process, to the extent permitted or required by law
  • To protect the security and safety of individuals, data, assets and systems, consistent with applicable law
  • In connection the sale, joint venture or other transfer of some or all of its company or assets, subject to the provisions of this Privacy Notice
  • To investigate or address actual or suspected fraud or other illegal activities
  • To exercise its legal rights, including enforcement of the Terms of Use for this site or another contract
  • To affiliated Pearson companies and other companies and organizations who perform work for Pearson and are obligated to protect the privacy of personal information consistent with this Privacy Notice
  • To a school, organization, company or government agency, where Pearson collects or processes the personal information in a school setting or on behalf of such organization, company or government agency.

Links


This web site contains links to other sites. Please be aware that we are not responsible for the privacy practices of such other sites. We encourage our users to be aware when they leave our site and to read the privacy statements of each and every web site that collects Personal Information. This privacy statement applies solely to information collected by this web site.

Requests and Contact


Please contact us about this Privacy Notice or if you have any requests or questions relating to the privacy of your personal information.

Changes to this Privacy Notice


We may revise this Privacy Notice through an updated posting. We will identify the effective date of the revision in the posting. Often, updates are made to provide greater clarity or to comply with changes in regulatory requirements. If the updates involve material changes to the collection, protection, use or disclosure of Personal Information, Pearson will provide notice of the change through a conspicuous notice on this site or other appropriate way. Continued use of the site after the effective date of a posted revision evidences acceptance. Please contact us if you have questions or concerns about the Privacy Notice or any objection to any revisions.

Last Update: November 17, 2020